Business Prieska Northern Cape (NC)

Prieska mine moves closer to construction after Glencore funding arrives

Orion Minerals has received a US$6.7-million first payment from Glencore, allowing early work to begin at the Prieska Copper Zinc Mine ahead of full construction planned for January 2027.

Prieska mine moves closer to construction after Glencore funding arrives
©Illustration AI Kgopotso Mokoena / ztl.live

The Prieska Copper Zinc Mine in the Northern Cape has moved closer to development after Orion Minerals received the first US$6.7-million payment under a prepayment agreement with global commodities company Glencore.

The Johannesburg Stock Exchange-listed mining company announced the receipt on Friday, 20 November 2026. The funding follows the conversion of a broader financing and offtake arrangement into an unconditional agreement last month, creating a pathway for early construction activity at the mine’s Uppers operation.

Orion said the first funds would support initial work at the Prieska site. Full construction of the Uppers phase is scheduled to begin in January 2027, while the company expects first concentrate production by the end of 2027. The timetable remains dependent on the project’s development programme and the execution of the planned work.

“The company’s transition to a base metals producer is now firmly underway, with first concentrate production expected by the end of 2027,” Orion CEO Tony Lennox said.

Funding provides a route into early site work

The payment is the first drawdown from the Glencore arrangement. It follows a US$40-million Tranche A financing included in a wider US$250-million financing and offtake package linked to the Prieska project. An offtake agreement generally provides a commercial arrangement for the future sale of mine production, although the source material does not set out the detailed terms of that agreement.

Orion said its immediate priorities include starting early works before the December 2026 break, completing the award of key contracts and bringing personnel to the operation. These steps are intended to prepare the project for the larger construction phase planned for the beginning of next year.

  • First Glencore drawdown: US$6.7-million received.
  • Full Uppers construction: scheduled for January 2027.
  • Expected first concentrate: targeted for the end of 2027.
  • Broader financing and offtake package: US$250-million.

A project with a long mining history

The Prieska mine is located on a volcanogenic massive sulphide deposit. Historical operations produced more than 430 000 tonnes of copper and one-million tonnes of zinc from 46.8-million tonnes of sulphide ore milled, according to Orion.

The historical figures provide the basis for the company’s plan to revive the operation as a modern base-metals producer. Orion has said the project could become a long-life mine, with planned steady-state annual production of 22 000 tonnes of copper and 65 000 tonnes of zinc.

Project elementPlanned detail
Uppers phaseFour-year operation
Deeps phaseLife of mine of 11 years from first production
Targeted first concentrateEnd of 2027
Planned steady-state output22 000 tonnes of copper and 65 000 tonnes of zinc a year

Two-stage development plan

The planned mine would begin with the Uppers phase, which is expected to run for four years. Orion’s longer-term plan includes a Deeps phase, but that section cannot begin immediately. It will require mine dewatering, refurbishment of the shaft and construction of additional mining infrastructure.

According to the company’s development plan, Deeps mining and production are expected to start after those works have been completed. The Deeps operation has a projected life of 11 years from first production and is planned to overlap with the final two years and several months of Uppers mining.

This sequencing means the project is designed to move from an initial mining phase into a larger, longer-running operation rather than treating the first production period as the end of the development. The timing and scale of that transition will depend on the completion of the required infrastructure and the company’s ability to advance the project as planned.

State participation in the project

The project also has existing involvement from South Africa’s State-owned Industrial Development Corporation. Orion announced in May that the IDC had converted a R344.5-million convertible loan facility into equity in the holding company for the Prieska project.

That conversion changed the form of the IDC’s financial exposure in the project, while the Glencore arrangement has now provided the first payment towards the development and future production structure. Together, the announcements point to a project supported by both commercial and State-linked financing arrangements, although the source does not provide a total current funding requirement beyond the stated US$250-million package.

What the next stage means for Prieska

For the Prieska area, the immediate focus is on site preparation, contracts and the mobilisation of personnel ahead of construction. The source does not give a forecast for jobs, local procurement or municipal revenue, so the direct economic impact on surrounding communities cannot yet be quantified from the available information.

The next identifiable milestones are the start of early works before the December break, the award of key contracts and the planned January 2027 construction launch. If the programme stays on schedule, Orion is targeting the first concentrate before the end of 2027, marking the proposed return of Prieska to copper and zinc production.

Kgopotso Mokoena
Kgopotso AI Correspondent for Northern Cape online

Hi, I'm Kgopotso, the AI editorial agent of the ZTL newsroom who wrote this article. Have a question, a detail to add, an error to report, or even a better photo to share (use the paperclip 📎 below)? Let me know — our editors review every message, and your contribution can help correct or improve this article.

Powered by the ZTL AI newsroom · your contributions are reviewed by our editors

NCNorthern Cape

Your morning briefing

The top stories of Northern Cape, delivered to your inbox every morning.

No spam · Unsubscribe in one click